Owner�s Engineer for
the Coal Handling Systems
of the new
700 MWe Longview Power Plant
Client
Longview Power, LLC
85 Wells Avenue, Suite 300
Newton, MA 02459-3215
Completion Date
October, 2008
Project Description
Energy Associates began working
on the project in 2001, when the site was first being investigated for a
coal-fired power plant by GenPower. At that
time, primary system parameters and design concepts for the coal, limestone,
and ash handling systems were formulated by Energy Associates. During the
next several years, GenPower moved forward with
project development, permitting, and contracting concepts for the plant.
The supercritical boiler was directly purchased from Foster Wheeler and
assigned to the selected contractor, a consortium of Siemens and Aker
Kvaerner. The consortium was responsible for the complete plant with one
major exception, the plant�s coal handling system.
When
the project was approved and financially closed in January, 2007, Longview
Power engaged Energy Associates as their engineer for the four (4) coal
handling systems needed for the project. These include the coal handling
system at the plant itself in Maidsville, WV; a coal
blending system (MEPCO Blending Yard) that was added to an existing coal preparation
plant that is adjacent to the power plant site; the Dooley Run Terminal located
near the primary fuel source for the plant, the 4-West Mine; and a four+ mile
overland conveyor system that links the Dooley Run Terminal, which is located
in Dunkard Township, Greene County, Pennsylvania to
the MEPCO Blending Yard, which is located in Maidsville,
West Virginia � an interstate overland conveyor system.
Energy Associates completed
a number of studies to define the four (4) coal handling systems. In one
study, coal properties were investigated and these directly influenced the
design of the plant�s coal handling system. It was found that this
relatively low grade fuel has poor flow characteristics, which affected the
some elements of design being considered. The design of the
stacking/reclaiming portion of the system was modified to suite test
results. In other studies, the preferences/input of MEPCO (the mine owner
and operating company for the Dooley Run Terminal, overland conveyor system, and
the blending yard) were addressed and key issues incorporated into the
design.
Energy Associates prepared
the bid specifications and bid drawings for the project. The coal
handling systems were awarded in three (3) stages; the Dooley Run Terminal and
overland conveyor system were bid as a package. Energy Associates
completed the technical evaluations and reviewed the cost proposals/options
submitted by each bidder.
Because
the power plant EPC consortium had a design/construction head-start on the EPC
coal handling contractor, the bid drawings for the coal handling system
included numerous details and a specific footprint/foundation design.
This allowed plant systems, through which the coal handling system threads, to
proceed in confidence that physical requirements were being considered - the
work was being coordinated.
The photographs view the Longview
Plant during construction. �The crusher
house and plant feed system to boiler silos are visible in two of these
pictures.� Note the proximity of the
scrubber and tanks behind the conveyor system and plant roadways and a water
runoff retention pond.