Cerrej�n Coal Mine Expansion Pre-Feasibility Study
Client
Ingetec, S.A. |
for |
Cerrej�n�s Partners: |
Completion Date
September, 2011
Project Description
The original Central
Plant for the Cerrej�n Coal Mine was developed to
provide high rail loading rates to make the dedicated unit train rail
transportation system efficient, while minimizing the initial capital cost for
the coal processing, handling, and storage facilities.� Initially, with a low annual capacity for the
mine, there were only a few trains to load each day.� The 12,000 ton coal silos could be filled at
a relatively low rate between trains.�
Run-of-mine (ROM) coal was stored near the truck hopper to provide a
ready stockpile of coal to supplement truck deliveries from the mine pit to the
truck hopper.
In 1985 when Exxon was a
major partner in the project, the original design capacity of the Cerrej�n Coal Mine was 15 MTPA and two (2) unit trains were
sufficient to meet this capacity.�
Modifications and expansions, including adding Plant No. 2, have
increased the Central Plant�s capacity to today�s 32 MTPA.� Currently there are five (5) unit trains
operating.� The railroad mainline from
the mine to the port is 150 km long.�
Trains complete a cycle in 12 hours.�
Pictured above is a view of Plants No. 1 (left conveyor) and 2 (right
conveyor) of the Central Plant and the ROM coal stockpiles, as viewed from the
top of train loadout silos.
Cerrej�n plans to expand their existing open-pit coal
mine in Colombia from 32 million tons per annum (MTPA) capacity to 60 MTPA.
Conceptual studies on different aspects of this program were undertaken by
several engineering/consulting firms.�
Different options for siting the process equipment, transportation
infrastructure, and shipping facilities were analyzed.� From these conceptual studies, Cerrej�n identified four (4) alternatives for the
pre-feasibility phase. These alternatives increase production capacity of the
existing Central Plant�s facilities to either 50 or 60 MTPA or construct a new
20 or 30MTPA Satellite Plant in the Caypa area.
Cerrej�n engaged INGETEC to investigate the expansion
alternatives for the Central and Satellite Plants and for the diversion of the
Rancheria River.� The Rancheria River and
a tributary courses through some of the new mine pits and portions of the site
for the Satellite Plant.� The
pre-feasibility work for the expansion alternatives includes the preparation of
study drawings, equipment lists, budgets, project schedule, and description of
the recommended option.
The increased demands for
coal in China, India, Chile, etc. and the expansion of the Panama Canal are
opening new opportunities for Cerrej�n.� The expansion program will help Cerrej�n to reach these markets.